Back on park today, Lift hill, new paving and fencing seemed the main focus today. There were workers everywhere they look to be busting a gut to get this thing open.
Lift hill
The lift chain waiting to be fitted to the first lift hill.
Attaching the chain
Lowering it into position
Chain is complete
Empty lift chain boxes to prove it
Theming & Queue line
Queue line tunnel
Fitting the screens at the half way point
Theming signs have been fitted
Footers
Footers have been or are being filled in all over the site
Exit area paving.
The exit area is starting to come together with nice new paving
Exit doors clearly visible
Here is the exit route which leads nicely to Oblivion, Enterprise and Submission.
Support
Of course we are still waiting on the support to be fixed, without this complete we cant get trains on track.
Overviews
A few overviews to finish the update, an update just wouldn't be an update without them.