Found out from talking with PSI threshold inspector that HP had inspections schedule for both Saturday 8/11and Sunday 8/12 with a concrete pour at 10 pm Sunday night. The city had not been informed and no inspection was schedule for Plumbing or Electrical for that weekend. Called Ryan at 8am and talked with him, was informed at that time that there would not be any inspection until Monday and the pour would be Monday night. Late that afternoon HP called downtown and asked for a plumbing inspection for Sunday afternoon, I was called by Thea Walker at 4:15 PM and was informed of the request by HP for the OK to make pour with only the Threshold performing the inspection (building only) I asked if there was any Electrical in this pour since no after hour inspection was requested was told by Lynn with HP with both Gene (Univeral) and Thea that there was no Electrical in this pour. On Monday the plumbing inspector called and informed me that there was conduit in the pour. At 11 am Monday a meeting was held with Univeral and HP where Lynn informed everyone present that the electrical conduit was installed after he left at 6pm.