Just wanted to provide a quick update on these inspections. Unfortunately, only one of them was partially completed on 3/30 and the rest were cancelled because
(and I'm sorry if this is too technical) the equipment that's used for the building's radio signals and coverage (BDA/DAS) was not located in a room with a 2-hour rated wall:
The good news is this issue seems to have been corrected because almost every open permit for this project
(8 of them) has its final inspection scheduled for tomorrow morning at 6a.
So uhhh, maybe that lagoon waterfront area will be opening up soonish?